OFFICIAL NOTIFICATION
Santa Monica Airport Removal of Excess Pavement Project

The purpose of this notice is to inform you that the work to remove the excess pavement for sections of the Airport that, as a result of the reduction of the runway to an operational length of 3,500 feet, are no longer used for aviation purposes is scheduled to begin on Sunday, June 16, 2019.  It is anticipated that the project will be completed by September 6, 2019 and will consist of several phases.  Each phase of the project will entail specific closures of the Airport.
 
Sully-Miller Construction, a highly regarded construction firm experienced with aviation projects, has been selected to remove and pulverize excess pavement from areas of the Airport that are no longer needed for aviation purposes, and to hydroseed certain parts of those areas.   
 
The Removal of Excess Pavement will consist of several phases: 
  • Phase 1:  Commences Sunday, June 16, 2019 and concludes Friday July 5, 2019 (excluding July 4).  During Phase 1, work will be performed nightly from 9:00 pm to 7:00 am, Sunday night through Friday morning.  The Airport will be closed to all aircraft operations during the aforementioned hours. 
  • Phase 2: Commences Monday, July 8, 2019 and concludes Thursday, July 11, 2019.   During Phase 2, work will be performed both during the day and night hours.  The Airport will be closed to all aircraft operations for 4 consecutive days, 24 hours per day 
  • Phase 3: Commences Sunday, July 14, 2019 and concludes Friday, August 2, 2019. During Phase 3, work will be performed nightly from 9:00 pm to 7:00 am, Sunday night through Friday morning.  The Airport will be closed to all aircraft operations during the aforementioned hours. 
  • Phase 4: Commences Monday, August 05, 2019 and concludes Thursday, August 08, 2019.   During Phase 4, work will be performed both during the day and night hours.  The Airport will be closed to all aircraft operations for 4 consecutive days, 24 hours per day 
  • Phase 5:  Commences Sunday, August 11, 2019 and concludes on Friday September 6, 2019 (excluding September 2). During Phase 5, work will be performed nightly from 9:00 pm to 7:00 am, Sunday night through Friday morning.  The Airport will be closed to all aircraft operations during the aforementioned hours.
 
Notices to Airmen will be issued ahead of these closures. For construction related questions and/or concerns please contact Brian Ochoa at brian.ochoa@smgov.net.  For all other inquiries please contact the Airport at  airport@ smgov. net.
 
We thank you in advance for your cooperation and patience as we work expeditiously to complete this project.
 
Sincerely,
Stelios Makrides
Airport Director


 
Visit www.smgov.net/airport for regular updates.
 
City of Santa Monica
Department of Public Works, Airport Division
Office of the Airport Director 
3223 Donald Douglas Loop South
Santa Monica, California 90405-3213
Tel: (310) 458-8591
Fax: (310) 572-4495
 
You signed up for email communications from the City of Santa Monica from one of our departments. If you would no longer like to receive emails, unsubscribe from this list. You can also update your preferences.