Throughout the week of February 18, we’ll continue saw cutting and replacing sidewalks and sections of road pavement on the Green Lake Loop. We’ll also continue replacing sections of road pavement and sidewalks on both N 40th St and N 50th St.

See below for more information about new and continuing work planned for the week of February 18.


 
What’s New:

Due to President’s Day, we will not be working Monday, February 17.


N 40th St:
  • Wallingford Ave N: We will begin work at this intersection as soon as Tuesday, February 18. Expect shifted travel lanes and pedestrian detours.
N 50th St:
  • 5th and 7th Ave NE: We have completed upgrading sidewalks and curb ramps on the north side of the street at this intersection. Expect closed sidewalks and pedestrian detours as we complete work on the south side of the street. We anticipate completing this work as soon as early next week, weather depending.
  • Due to winter weather, we now anticipate completing this work as soon as the end of February. We will return in late spring or early summer to complete final asphalt paving on N 50th St.
What’s Continuing:
  • Work Monday - Friday, from 7 AM to 7 PM 
  • For more information on our typical construction impacts, please visit our project website
N 40th St:
  • From Stone Way N to Wallingford Ave N: expect pedestrian detours, shifted travel lanes, and traffic occasionally reduced to a single lane with flaggers present to rotate traffic
  • From Wallingford Ave N to Latona Ave N: expect pedestrian detours and shifted travel lanes
N 50th St:
  • East of I-5: expect pedestrian detours, shifted travel lanes, and lane closures with one lane maintained in each direction
  • Stone Way N to I-5: expect pedestrian detours, shifted travel lanes, lane closures, and traffic occasionally reduced to a single lane with flaggers present to rotate traffic
    • We may have to deactivate signals at Latona Ave N and Thackery Ave N to make utility repairs in the intersections. Uniformed police officers will be present to direct traffic when this occurs.
Green Lake Loop
  • Green Lake Way N: We are working near N 52nd and N 53rd streets and will be continuing north. Expect pedestrian detours and shifted travel lanes.
  • The intersection of West Green Lake Way N and East Green Lake Way N: expect noise, pedestrian detours, and the island to be removed to maintain two-way traffic while we work
New island at the intersection of N 50th St and 7th Ave NE

What we’ve heard: 
Each week, we’ll plan to answer a few frequently asked questions from the community.

How should people walking travel through the intersection of N 50th St and 7th Ave NE?
We know that work at these intersections has created significant impacts for both people driving and people walking. We have completed work on the sidewalk and curb ramps on the north side of the street at this intersection, which will allow for people to easily and safely walk through the intersection. While we are working on the south side of N 50th St, people walking will detour to the north side of the street.

How long will work continue on N 40th St?
We anticipate continuing repair work on N 40th St for another 3 to 4 months. This includes rebuilding sidewalks, curb ramps, roadway panels, and utility work. We will return in the summer to do final surface paving along N 40th St.

 

We are coordinating with Puget Sound Energy (PSE) who is also working in the area.

PSE's natural gas project is doing work on N 80th St and preparing to start work on N 50th St at Stone Way N. If you have questions about their work, you can contact them at  425-505-3768 or MajorProjects@pse.com.

 

Please share this email with others who might be interested in receiving project information and construction updates, and feel free to get in touch with us if you have any questions.

How to stay informed

Call us (206-693-4151) or email us (greenlakepaving@seattle.gov) with questions during construction


The City of Seattle is paving portions of N 40th St, N 50th St, N 80th St and streets on the east side of Green Lake as soon as 2019. To request translation of these materials, call 206-693-4151.
La Ciudad de Seattle pavimentará porciones de las calles N 40th St, N 50th St, N 80th St y calles en el lado este de Green Lake a más tardar para el 2019. Para solicitar la traducción de este material, llame al 206-693-4151.
西雅图市政府最快将于2019年铺设以下的部分路面:N 40th St, N 50th St, N 80th St以及 Green Lake 东边的街道。如 需這些資料的譯文,或是在會議時需要口譯服務,請 致電 206-693-4151。

Twitter
Facebook
Website
Copyright © 2020 Seattle Department of Transportation, All rights reserved.
You are receiving this email because you signed up for project updates for Green Lake Area Paving and Safety Projects.

Our mailing address is:
Seattle Department of Transportation
P.O. Box 34996
Seattle, Wa 98124-4996
Add us to your address book

Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Seattle Department of Transportation · P.O. Box 34996 · Seattle, Wa 98124-4996 · USA

Email Marketing Powered by Mailchimp